Study on stability of small oscillation transient process of hydropower station with long-distance diversion tunnel

Jiao Yun-qiao,Jiang Chunbo,Kong Qingrong,Zhang Yong-liang
2009-01-01
Abstract:Taking the Jinping II hydropower station for an example, the stability of small oscillation transient process with long-distance diversion tunnel is analyzed by numerical calculation. The stability of small oscillation is investigated when the generating unit has no load, the stability of small oscillation by effect of the chamber area, water head loss coefficient of surge tank and the roughness of the tunnel are also investigated. The results of the investigation suggest that the no-load condition meets the need of safety, the chamber resistance as well as the roughness of tunnel has great influence on the stability of small oscillation transient process, the head loss coefficient of surge tank only has a little influence on the stability.
What problem does this paper attempt to address?