Scheduling model for section of sintering-blast furnace

Daguang Lu,Chenguang Bai,Dong Liang,Guibao Qiu,Wenjuan Juan Niu
2009-01-01
Abstract:The section of sintering and BF (blast furnace) is very important in iron-making process. In practice, the scheduling is so extensive that three faults unfavorable to continuous product will be easier to happen. This paper introduces the integration Petri Net and GA (genetic algorithm) as suitable tools for simulation and optimization of scheduling to section of sintering- BF under a certain hot iron order. The situation of the iron plant Chongqing Iron and Steel Company is researched in approach above mentioned. By analysis, the conclusion is drawn that scheduling with optimized values can maintain continuity of key operations, can satisfy order of hot iron in maximal degree and can keep the best stability of key storages.