Study on dynamic production planning system oriented to shipbuilding process

Xiaobing Liu,Zhongkai Li,Xiao Wang,Wenliang Zhao
DOI: https://doi.org/10.1109/08IAS.2008.155
2008-01-01
Abstract:To reduce the costs and lead time for shipbuilding, an integrated system is proposed to optimize a long term production plan, as well as the node plan and the physical distribution plan. A hierarchical architecture and the object-oriented technology are used to incorporate all critical information such as production capacities. A physical distribution algorithm is developed assuming the material quantities consumed follow normal distribution. A simplified simulated-annealing algorithm is presented to increase the planning optimization speed. The system was tested as feasible and effective in a case study conducted at the Dalian Shipbuilding Industry Co., Ltd. in China. © 2008 IEEE.
What problem does this paper attempt to address?