Assessment of sediment trapped by the Manwan Dam on Lancang River

HE Da-ming
2008-01-01
Abstract:Jiuzhou and Gajiu stations are the two hydrological stations for mornitoring input and output sediment of the Manwan Reservoir on Lancang River.There existed 28-year measured sediment data at the stations,and their annual suspended sediment loads correlate well.This relationship was established through regression analysis.After the operation of the Manwan Dam in 1993,the relationship model was used to calculate the natural sediment loads in 1993-2003 at Gajiu station based on the measured annual sediment load at Jiuzhou station.So the difference between the natural and measured sediment loads at Gajiu station is thought to be the reservoir sedimentation of the Manwan Dam.Calculation results show that annual sediment trapped by the Manwan Dam was about(2.69~2.85)×10~7t,total sedimentation deposited in the reservoir was(29.59~31.35)×10~7t in the period of 11-year operation,annual loss of reservoir capacity was(2.07~2.19)×10~7m~3,total loss of reservoir capacity was(2.276~2.412)×10~8m~3 till 2003,accounting for 21.5%~22.8% of the storage capacity of the Manwan Reservoir.This research could be a reference to assess the impact of hydropower station construction on the downstream sediment variation and the operation of the Manwan Dam in the future.
What problem does this paper attempt to address?