Risk Analysis on Entrance with Shallow-buried and Unbalanced Pressure of Jiqingling Tunnel and the Measures

王海明
DOI: https://doi.org/10.3969/j.issn.1672-7428.2010.01.022
2010-01-01
Abstract:Based on the engineering case in Jiqingling tunnel, risk analysis was made on the construction of tunnel entrance in poor geological condition with shallow-buried and unbalanced pressure.Integrated prevention measures for geological diseases were put forward with early support strengthening,short cycling excavating and early support closing.
What problem does this paper attempt to address?