The South to North Water Diversion Project and Its West Line
ZHANG Jing-jian,FU Bing-jun,LI Zhong-kui
DOI: https://doi.org/10.3969/j.issn.1002-5634.2008.05.001
2008-01-01
Abstract:The south to north water diversion project in China consists of three main parts:western line,middle line and eastern line,which will divert water from the upper,middle and lower reaches of the Yangtze River to northwestern and northern China respectively.The total volume of water transferred is about 448×108 m3.After describing briefly the necessity and the layout of the project,based on the analysis of local environment,geological conditions and so on,double shield TBMs are recommended to be used for rapid excavation of the most part of the tunnels.In addition,several key countermeasures concerning ventilation,high geostresses,active faults,squeezing rocks,rock burst,high pressure water inflow,et al,are discussed.Finally,some suggestions are put forward.