Forecast Model of Activity Duration Based on LS-SVM in Construction Engineering Project

祁神军,张云波,丁烈云
2010-01-01
Abstract:Referring to fuzziness and randomness for activity duration forecast of construction engineering project by traditional ways,the influence factors of activity duration are analyzed,and parameter calculation is also proposed.A forecast model of activity duration based on the least square support vector machine(LS-SVM) is set up,and the analysis of a subway case confirms validity of this model.The model is trained by the schedule execution situation of the activities in other similar projects or the similar activities in the same project,the activity duration simulated by the model conforms with the request of schedule controlling.In the forecast model of activity duration based on LS-SVM,the prediction and network total errors is less,training time is shorter than the ones in he forecast model based on BP.