Design and Treatment on Asphaltic Concrete Facing of Upper Reservoir in Tianhuangping Pumped Storage Power Station

Zhang Chunsheng,Zhang Kezhao
DOI: https://doi.org/10.3969/j.issn.0559-9342.2007.01.013
2007-01-01
Abstract:The engineering geological conditions of the upper reservoir in Tianhuangping Pumped Storage Power Station are very complex.The simple asphalt concrete facing is adopted for whole reservoir bottom except the inlet and outlet area.There were 34 cracks on the asphalt concrete impervious face slab during the early operation period.After repairing,the seepage has not increased since May of 2001.Because the asphalt concrete can be repaired quickly and it can impound water immediately after repairing,the adoption of asphalt concrete facing has certain advantage.