An Improved Iterated Greedy Algorithm for the No-Wait Flow Shop Scheduling Problem with Makespan Criterion

Quan-Ke Pan,Ling Wang,Bao-Hua Zhao
DOI: https://doi.org/10.1007/s00170-007-1120-y
IF: 3.563
2007-01-01
The International Journal of Advanced Manufacturing Technology
Abstract:An improved iterated greedy algorithm (IIGA) is proposed in this paper to solve the no-wait flow shop scheduling problem with the objective to minimize the makespan. In the proposed IIGA, firstly, a speed-up method for the insert neighborhood is developed to evaluate the whole insert neighborhood of a single solution with (n − 1)2 neighbors in time O(n 2), where n is the number of jobs; secondly, an improved Nawaz-Enscore-Ham (NEH) heuristic is presented for constructing solutions in the initial stage and searching process; thirdly, a simple local search algorithm based on the speed-up method is incorporated into the iterated greedy algorithm to perform exploitation. The computational results based on some well-known benchmarks show that the proposed IIGA can obtain results better than those from some existing approaches in the literature.
What problem does this paper attempt to address?