A Resources Dynamic Distributing Model under Multi-Projects Construction Based on Genetic Algorithm

ZHANG Wei-hong,LIU Jian-min,ZHANG Yu-jie
DOI: https://doi.org/10.3969/j.issn.1673-7644.2008.01.003
2008-01-01
Abstract:By taking the minimum lost caused by insufficient resource supply as an objective,a resources dynamic distributing model under multi-projects construction was founded which based on small time intervals and resources supply changing with time.Further,for manpower resources,integer distribution model was made based on the delayed time calculated by the mentioned model above.For the above two models,issues of application were discussed based on genetic algorithm.