ANN prediction model of final construction cost at an early stage

Khalid S. Al-Gahtani,Abdullah M. Alsugair,Naif M. Alsanabani,Abdulmajeed A. Alabduljabbar,Abdulmohsen S. Almohsen
DOI: https://doi.org/10.1080/13467581.2023.2294883
IF: 0.904
2024-03-14
Journal of Asian Architecture and Building Engineering
Abstract:Previous studies developed models to predict final construction cost (FCC) values based on many inputs, which makes them difficult to use. However, relying on models with relatively few inputs will reduce the accuracy of the prediction results. This paper aims to develop an artificial neural network (ANN) model to predict the FCC based on contract cost (CC), contract duration, and project sector at an early stage of a project. The data collected and used for the ANN model was 135 Saudi Arabian construction projects. The Zavadskas and Turskis logarithmic approaches, and the Pasini method were utilized to overcome the limited data. Then, the ANN model was developed through two stages. The purpose of the first stage was to enhance the data by identifying the abnormal data using absolute percentage errors (APE). The enhanced data was used to develop the ANN in the second stage. The finding showed that the ANN model provided an average MAPE (mean absolute percentage error) of 18.7%. The MAPE of the ANN model is decreased to 8.7% on average by deleting data with an APE higher than 35%. The model allows stakeholders to evaluate the financial importance of potential risks and develop appropriate risk management strategies.
construction & building technology
What problem does this paper attempt to address?
The paper attempts to address the problem of predicting the final construction cost (FCC) in the early stages of construction projects based on contract cost (CC), contract duration (CD), and project department type. Specifically, the goal of the paper is to develop an artificial neural network (ANN) model that can utilize fewer but key input variables to improve prediction accuracy and assist stakeholders in budget planning and decision-making. Additionally, by comparing the predicted final contract cost with the actual cost upon project completion, the model can also serve as a tool for evaluating construction project performance. Since existing prediction models often rely on a large number of input variables and are difficult to use, this study aims to simplify the model while maintaining high prediction accuracy.