Time Allocation and Long-Term Scheduling of ESO Telescopes at La Silla Paranal Observatory

M. Rejkuba,O. R. Hainaut,T. Bierwirth,M. Pruemm,A. Weiss
2024-07-22
Abstract:The preparation of the long-term telescope schedule follows the submission and scientific review of new proposals. At the European Southern Observatory (ESO) this process entails scheduling the scientific proposals according to their scientific merit and available observing resources, as well as scheduling technical, maintenance, and commissioning activities for all operational telescopes of the La Silla Paranal Observatory. After the recent overhaul of the phase 1 proposal submission software, ESO started the development of a new telescopes time allocation and scheduling tool. The new tool makes the scheduling process more efficient while optimising the use of observing facilities. Besides scheduling activities and allocating time according to scientific merit, available resources, operational and programmatic needs, the tool will enable simultaneous scheduling of multiple telescopes to appropriately account for dependencies between them. The implementation of this new Time Allocation tool opens the possibility for dynamic re-scheduling of the telescopes, which is a pre-requisite to implementing a "Yearly Call for Proposals" along with the "Fast Track Channel" at ESO.
Instrumentation and Methods for Astrophysics
What problem does this paper attempt to address?
The problem that this paper attempts to solve is to optimize the telescope time allocation and long - term scheduling at the La Silla Paranal Observatory (LPO) of the European Southern Observatory (ESO). Specifically, the paper focuses on the following aspects: 1. **Enhancing scientific output**: By more efficiently allocating telescope time, ensure that the scientific output of the observatory is maximized according to the scientific value of the proposals and the available resources. 2. **Multi - telescope - dependent scheduling**: Achieve the simultaneous scheduling of multiple telescopes to properly consider the dependencies between them, especially for complex instruments that require parallel operation (such as ESPRESSO, VLTI, etc.). 3. **Dynamic rescheduling**: Develop a tool that can dynamically reschedule telescope time, which is a prerequisite for implementing the annual "Call for Proposals" and "Fast Track Channel" (FTC). 4. **Handling a large number of proposals**: As the number of submitted observation proposals continues to increase (currently about 900 every six months), more efficient tools are required to handle these proposals and rationally arrange the observation time. 5. **Integrating technical, maintenance and debugging activities**: Incorporate the Technical Time Requests (TTR) into the scheduling process together with scientific observations, ensuring that necessary maintenance and technical activities are arranged without affecting scientific observations. To this end, ESO has developed a new time allocation and scheduling tool (TA2), aiming to simplify and optimize this complex process. TA2 not only improves the scheduling efficiency but also provides flexibility and support for future scheduling requirements.