Robust Dynamic Transmission and Renewable Generation Expansion Planning: Walking Towards Sustainable Systems

Cristina Roldán,Agustín A. Sánchez de la Nieta,Roberto Mínguez,Raquel García-Bertrand
DOI: https://doi.org/10.1016/j.ijepes.2017.09.021
2017-01-30
Abstract:Nowadays, the transition from a conventional generation system to a renewable generation system is one of the most difficult challenges for system operators and companies. There are several reasons: the long-standing impact of investment decisions, the proper integration of renewable sources into the system, the present and future uncertainties, and the convenience to consider an integrated year-by-year representation of both uncertainties and investment decisions. However, recent breakthroughs in Dynamic Transmission Network Expansion Planning (DTNEP) have demonstrated that the use of robust optimization might render this problem computationally tractable for real systems. This paper intends to consider not only the capacity expansion of lines, but the construction and/or dismantling of renewable and conventional generation facilities as well. The Dynamic Transmission Network and Renewable Generation Expansion Planning (DTNRGEP) problem is formulated as an adaptive robust optimization problem with three levels. First level minimizes the investment costs of transmission network and generation expansion planning, the second level maximizes system operational costs with respect to uncertain parameters, while the third level minimizes those operational costs with respect to operational decisions. The method is tested for two cases: i) an illustrative example based on Garver IEEE system and ii) a case study using the IEEE 118-bus system. Numerical results from these examples demonstrate that the proposed model allows making optimal decisions towards reaching a sustainable power system, while overcoming problem size limitations and computational intractability for realistic cases.
Optimization and Control
What problem does this paper attempt to address?