Integrated Multi-Objective Optimization Of Predictive Maintenance And Production Scheduling: Perspective From Lead Time Constraints

Zhi-jia Zhao,Qilong Yuan
DOI: https://doi.org/10.56578/jimd010108
2022-09-30
Abstract:For the integrated optimization of job-shop production scheduling and predictive maintenance, this paper fully considers such constraints as product delivery time and changing machine failure rate, and establishes a multi-objective optimization model aiming to minimize the processing cost and the product processing time. The model includes the changing machine failure rate into the integrated optimization of job-shop production scheduling and predictive maintenance, and enables the prediction of the machine state according to the processing time of the current job, laying the basis for the decision-making of the machine activity and the reasonable and effective production planning. In addition, the non-dominated sorting genetic algorithm (NSGA)-II was designed to solve the proposed model. The algorithm performance was improved through the operator crossover and mutation by the simulated binary crossover algorithm (SBX). The proposed strategy was verified through a case study.
Engineering
What problem does this paper attempt to address?
### Problems Addressed by the Paper This paper primarily investigates the multi-objective optimization problem of integrating predictive maintenance with production scheduling, considering product delivery time and machine failure rate variations. Specifically, the paper establishes a multi-objective optimization model to minimize processing costs and product processing time, and employs the Non-dominated Sorting Genetic Algorithm II (NSGA-II) to solve this model. **Main research contents include:** 1. **Problem Background**: - In actual production, due to the insufficient consideration of machine performance degradation and maintenance, production plans often fail to achieve the expected results. - Integrating predictive maintenance with production scheduling can ensure the normal operation of production plans, improve workshop processing efficiency, enhance product quality, effectively control machine maintenance costs, and achieve reasonable allocation of internal resources within the enterprise. 2. **Model Establishment**: - Considering product delivery time and cost factors, machine failure rates are incorporated into the workshop production scheduling with predictive maintenance. - A multi-objective integrated optimization model considering machine state constraints and task delivery time is established. 3. **Algorithm Design**: - A Non-dominated Sorting Genetic Algorithm II (NSGA-II) based on the Simulated Binary Crossover (SBX) operator is designed to solve the proposed model, and the effectiveness of the proposed strategy is verified through case studies. 4. **Experimental Analysis**: - Through an instance analysis of a workshop containing 6 jobs, a multi-objective Pareto solution set is generated, and the accuracy of the Pareto solution set is analyzed, further proving the feasibility and effectiveness of the model. In summary, this paper aims to address the challenges brought by delivery time and machine failure rate variations in actual production by integrating predictive maintenance with production scheduling, thereby achieving an effective balance between production cost and time.